Work has officially started on the £20 million restoration of Huddersfield Open Market, with contractors moving onto the site to begin the main construction phase.

Willmott Dixon is carrying out the renovation of the Grade II* listed Victorian market hall, with hoardings now installed around the building to separate the works from shoppers and traders at the nearby temporary market.

Kirklees Council says the restoration of the market hall and surrounding Market Yard is due to be completed by spring 2028.

Council officials had previously said the market hall would reopen in January 2028, with work on the outdoor areas completed shortly afterwards.

The Government’s £16.5 million Levelling Up Fund grant, which is helping to pay for the project, must be spent by March 2028.

The start of construction comes after the cost of the scheme increased by around £3.5 million to £19.985 million.

As Huddersfield Hub revealed last month, unexpected problems with the market hall’s roof and other additional costs forced Kirklees Council to divert money from other projects to meet the increased bill.

The restoration will see the market hall’s decorative cast-iron frame repaired, its famous glazed roof renewed and the building’s original colour scheme of traditional reds, pinks and creams brought back.

The renovated market will have 87 pitches, including up to 12 permanent stalls with built-in services and storage, and 75 movable stalls.

The movable pitches will be around 50% larger than the existing ones, giving traders more space and allowing the hall to be rearranged for events.

There will be three hot food outlets, an enclosed and heated market café and a small bar to support events and evening activities.

Accessibility improvements will include ramps, automatic doors, accessible toilets and a Changing Places facility.

Outside, the Market Yard will have space for further trading pitches and events.

The redevelopment has proved controversial, with traders and campaigners raising concerns over the closure of the historic market hall, the reduction in indoor stall numbers and the possible loss of traditional market trading.

 

 

The temporary market, between Brook Street and the Tesco car park, opened in August and will remain in operation throughout the construction work.

The council’s latest financial report, presented to Cabinet on October 6, set out how spending on the market scheme is expected to be spread over the next two financial years.

The capital programme includes £8 million for 2026/27 and another £8.958 million for 2027/28. These figures exclude expenditure from previous financial years.

But the council is also facing a challenge to ensure the investment produces a market that costs less to run.

Its latest budget strategy includes a temporary £100,000 reduction in expected income from its markets service during 2027/28 while redevelopment work takes place in Huddersfield and Dewsbury.

Council officers say the income budgets will be reinstated once the schemes are completed and financial plans are being developed to reduce the long-term subsidies needed to run the markets.

Clr John Hardie, Kirklees Council’s Cabinet member for regeneration, highways and transport, said: “Regenerating the historic market hall to secure its future, protect its heritage and build on the existing market offer Huddersfield has, is moving to its next exciting stage.

“People will have seen work take place on preparing the site for the renovation, but they will now see a lot more activity around this beautiful Grade II* listed building.

“The temporary market and stalls are still open as normal, offering a range of fresh goods and hidden gems, and our markets team will be continuing to work with traders and customers to support them as we move onto this next phase of work.

“The Huddersfield Market scheme is just one key part of revitalising the town centre as we look to deliver clear benefits for our local communities and people will be able to see the much-loved building carefully restored.”

 

 

Chris Yates, Yorkshire director for Willmott Dixon, said: “We’re delighted to be working in partnership with Kirklees Council to deliver a transformation of the historic Huddersfield Market Hall.

“This is an important project for Huddersfield, creating a refreshed market while paying tribute to its proud heritage to allow the Market Hall to continue supporting the town centre and local traders for many years to come.”

The renovation is one of several major projects taking place in Huddersfield town centre alongside the redevelopment of the bus station, the restoration of the George Hotel and the Our Cultural Heart scheme.

Kirklees Council is facing wider financial pressures, with a forecast overspend of £13.6 million in 2026/27 and a projected £24 million budget gap in 2027/28.

Although the market redevelopment is funded through a separate capital budget, the council’s financial strategy stresses the need to make its investment programme affordable and reduce the cost of borrowing.