TransPennine Route Upgrade works on track midway through 30-day closure of Huddersfield Railway Station

It’s approaching the half-way point of the 30-day closure of Huddersfield Railway Station and TransPennine Route Upgrade (TRU) has given an update on progress of the work.

A TRU spokesman said: “With a giant crane towering over the centre of the town, the middle of Huddersfield is currently a hive of activity with an army of people working night and day.

“The first two weeks of the 30-day closure have seen significant improvements carried out on John William Street bridge, with two new bridge decks now installed as part of strengthening upgrades to Huddersfield Viaduct. This will allow for additional tracks and overhead line equipment installation in the future.

 

 

“Inside the station platforms 1 and 2 have been demolished as part of the platform and track re-modelling works, which will see them lengthened, enabling longer trains with more seats to stop at the station.

“Across the wider route new track drainage and signals have also been installed.”

Since the closure engineers have:

  • Excavated over 13,000 tons of soil;
  • Installed 1.7 kilometres of new rail and 2,517 sleepers;
  • Laid more than 6,200 tons of ballast and stone;
  • Completed 3.9 kilometres of tamping to improve track stability.

 

 

Paul Sumner, TRU senior sponsor, said: “We’ve made great progress in the first half of the 30-day closure with major works that have been in planning for a while now coming to life.

“These activities take us a step closer to Huddersfield Station serving as a vital hub for a new era of rail travel across the Pennines, which is a major boost for the economy locally and regionally.

“A big thanks to our local businesses, residents and customers as we undertake these vital upgrades.”