Huddersfield Railway Station to be closed on four weekends before Christmas ahead of final 38-day shutdown

Following the 16-day closure of Huddersfield Railway Station, which ended on Sunday, more closures have been announced counting down to completion of the £70 million project in early 2027.
Transpennine Route Upgrade says the station will be closed on the following weekends: Saturday and Sunday October 10 and 11; Saturday and Sunday November 14 and 15; Sunday December 13; and Sunday December 20.
After that is the final 38-day closure from Christmas Eve through to Sunday January 31 2027.
If all goes according to plan the new-look station will re-open on Monday February 1 2027.
The latest 16-day closure saw engineers work around the clock across the railway and at Huddersfield and Deighton stations. This included:
  • Installation of two lines of track through the Huddersfield area, including more than 2km of new track, supporting future capacity improvements, and enabling faster services to overtake stopping trains;
  • More than 1.3km of track renewals and over 900 metres of drainage renewals to improve the reliability of services;
  • Significant progress at Huddersfield Station, including platform extensions, restoration of the station’s historic roof canopy and subway extensions;
  • Major upgrades at Deighton Station, including work to extend the platforms and the installation of a new accessible footbridge, which will have lifts once complete;
  • Installation of more than 50 overhead line equipment masts and over 50 steel structures to support future railway electrification;
  • Preparation works at the A62 Leeds Road bridge ahead of its future reconstruction to accommodate railway electrification, signalling installation to improve railway performance and reliability.
James Richardson, TRU managing director, said: “Completing this latest phase of work is down to the dedication, skill and teamwork of our teams.
“From infrastructure delivery to planning and keeping passengers on the move during the disruption to their journeys, every part of the programme has played a role in this latest work.”
Liam O’Shaughnessy, TRU programme delivery lead for Northern, said: “The work that has been completed over the last 16 days in the Huddersfield area is another crucial step towards delivering the benefits that the Transpennine Route Upgrade will bring for customers across the north.
“We have worked closely with our industry partners to keep customers on the move, and these works have continued, and we would like to thank customers and local communities for their patience and cooperation, whilst these improvement works have been taking place.”