Huddersfield and the £11bn Transpennine Route Upgrade: what’s still to come and the full timetable of key dates ahead

The Transpennine Route Upgrade is a massive £11bn engineering project that’s causing disruption across Huddersfield, with stations being revamped or rebuilt and huge work needed on tracks and overhead power lines.

It’s easy to lose sight of what’s yet to start, what’s still to complete, and the timeline of the major milestones to come. Hub journalist Andy Hirst has investigated – here’s his in-depth report.

The Transpennine Route Upgrade has already been years in the making … and there are another eight years to go before the first electric train will run on the entire 70-mile route from Manchester to York.

Even after that, work digitising the system will continue through to around 2038. But it’s important to keep in mind that passengers will see improvements and feel the benefit from the long-running £11bn scheme long before then.

In 2034, the journey time between Manchester and Huddersfield will be cut by four minutes from 28 minutes to 24, and between Huddersfield and Leeds from 19 minutes to 15.5 minutes.

Overall, it will knock 10 minutes off the journey from Manchester to Leeds and 14 minutes off the journey from Manchester to York.

But the faster times are only a small part of the improvements.

There will be far more passenger space on the trains, with peak hour capacity between Manchester and Huddersfield expected to more than double from around 1,500-1,600 passenger places now to between 3,100-3,300 places per hour in 2034.

There will be up to eight trains per hour running – four fast, two semi-fast and two local services.

Between Leeds and Huddersfield, capacity will increase by almost a third, from about 5,400 places now to between 6,900 and 7,100 places per hour, with eight trains running every hour.

Almost all the massive renovation work at Huddersfield railway station will be completed by February next year, with the station shutting on Christmas Eve and not reopening again until February 1.

Deighton station is being rebuilt, with this work due to finish in spring 2027.

 

Trains are expected to be quicker and more reliable on new tracks between Huddersfield and Leeds from 2028, with this stretch of the route electrified from 2030.

Work on the Transpennine Route Upgrade officially began in 2015 with early preparatory and overhead line work but expanded significantly by 2021 when the electrification work between York and Church Fenton started in February 2021.

Many people don’t realise that 25% of the route is already completed and electrified – these are the stretches between Manchester and Stalybridge and from Church Fenton to York.

The focus now is on the stretch from Church Fenton through Leeds to Huddersfield.

As part of the current work, several stations are being upgraded or totally rebuilt including Huddersfield, Deighton, Mirfield, Ravensthorpe, Batley and Dewsbury with most due to be finished in 2027 with work on Ravensthorpe concluded in 2028.

Work is being done on 23 stations across the entire route.

From 2028 the focus will be on the Gledholt to Standedge and Stalybridge to Diggle stretches, with the work running until 2034.

Work between Standedge and Gledholt will include huge changes at Marsden and Slaithwaite stations and the reconstruction or modification of bridges and roads so more tracks and overhead lines can be installed. Tunnels will also need to be modified to allow more space for the overhead lines.

 

 

Over the hill, Mossley station will be relocated and Greenfield station upgraded.

Transpennine Route Upgrade managing director James Richardson said: “TRU is all about faster, greener, cleaner journeys; better connections, more reliability and increased capacity for the long-term and all the economic benefit this will bring to the region.’’

That economic benefit is estimated to be around £368m.

TRU has more than 5,000 staff, with 85% coming from within 40 miles of the route and it will have created over 8,000 jobs, including 590 apprentices, during the entire scheme.

Mr Richardson added: “We’ve tried to employ as many local people as possible. We are training and developing the workforce not only for now but to work on future railway investment in the north of England over the years to come.’’

Looking forward, train operator TransPennine Express has ordered 29 new five-car electric trains to start running on the line from 2034 and they will have spacious interiors, more seats, wi-fi, power sockets and USB-C charging at every seat, real-time passenger information screens, cycle storage and extra luggage space.

 

 

Digital signalling is expected to be installed on the route from 2035. This is the rollout of the European Train Control System, which brings signalling information directly into the driver’s cab. Instead of relying on lineside signals, information will instead be displayed on a Driver Machine Interface with features also including continuous speed supervision and train protection.

Mr Richardson added: “This change is an important part of modernising the railway and supporting its safe operation. It will also enable enhanced performance and more efficient use of the network.’’

 

In summary, the main timelines from now are:

February 1, 2027: Majority of work completed at Huddersfield railway station

Spring 2027: Work on Deighton railway station finished

2028: Trains are expected to be quicker and more reliable on new tracks between Huddersfield and Leeds

2030: First electric trains running between Huddersfield and Leeds

2028 to 2034: Massive engineering work completed between Gledholt and Stalybridge through Slaithwaite and Marsden

2034: First electric trains will run on the entire 70-mile route from Manchester to York

2034: 29 new electric trains will start to run on the route

2035: Work starts on digitising the route which could take up to three years, hopefully bringing the entire project to a complete finish by 2038









More